Employ Accident Prevention Measures and Risk Mgmt Reviews
Initial Overall Level of Risk
26 of 32
<img src="../../images/a414p0080s02p0050V115.gif" width="760" height="445" border="0">
&pageText=Once you have completed the assessment of the risk for each identified hazard, you must determine the initial overall level of risk for the mission or task.& &pageText2= •  The initial overall level of risk     should be determined based     on the hazard having the     greatest risk.

•  If one hazard has a high risk,     the initial overall level of risk is     high also, no matter how many     moderate or low risk hazards     are present.

•  Once you have determined     the initial overall level of risk,     you will forward the worksheet     up the chain of command and     the commander completes the     worksheet and determines the     overall level of risk based on     the residual risk.& &textPosition=top& &mediaStyle=swf& &imageBorder=true& &imageYpos=70& &imageXpos=235&
Previous page
Click here to go to a specific page within the topic
Click here to view additional information for this course
Click here to hear the audio clip for the current page
Click here to view the video clip for the current page
Click here to view additional information for this page
Click here to view the options menu
Click here to go back to the most previously viewed page